Construction
Solera construction spend has overrun budget by +24.1%, ₹839 Cr actual against ₹676 Cr budgeted.Budget vs actual by project
₹ Cr
Monthly spend trend
₹ Cr
Total to date: ₹6,268 Cr actual against ₹5,993 Cr budget.
By project
| Project | Budget | Actual | Variance |
|---|---|---|---|
| Titanium SPR | ₹231 Cr | ₹232 Cr | +0.4% |
| Cloverdale SPR | ₹63.2 Cr | ₹58.8 Cr | -6.9% |
| Twin Tower DXP | ₹169 Cr | ₹174 Cr | +3.2% |
| De Luxe DXP | ₹653 Cr | ₹673 Cr | +3.1% |
| Daxin Vistas | ₹510 Cr | ₹539 Cr | +5.5% |
| City of Colours | ₹575 Cr | ₹592 Cr | +3.0% |
| Sarvam | ₹340 Cr | ₹355 Cr | +4.5% |
| City 92 | ₹459 Cr | ₹463 Cr | +0.7% |
| City 93 | ₹852 Cr | ₹873 Cr | +2.4% |
| The Serenas | ₹921 Cr | ₹923 Cr | +0.2% |
| Solera | ₹676 Cr | ₹839 Cr | +24.1% |
| Synera | ₹545 Cr | ₹546 Cr | +0.2% |